CONSTRUCTION OF A SMART ACCESS CONTROL SYSTEM
Location: Nhon Trach Industrial Park
Year of Commissioning: 2022
Status: Completed
Project Media Gallery

Site Logs & Engineering Solutions
Lắp đặt cửa phân làn swing gate, camera AI nhận diện khuôn mặt và phần mềm quản lý chấm công tập trung cho tòa nhà văn phòng.
Project Deployment Schedule
Week 1
Kick-off & Physical Survey
Delivery of camera units, LAN cabling media, ANPR systems, and GPS trackers to the site.
Week 2
Cable Tray & Path Execution
Technical crew routing cabling through protective insulated conduits for safety and aesthetics.
Week 3
Hardware Setup & Configuration
Mounting camera hardware, mapping local IP routes, configuring network routers, and systems integration.
Week 4
Acceptance Testing & Handover
Measuring throughput and data latency, handing over as-built cabling diagrams, and signing off reports.