Installing smart LAN & WiFi system at Minh Thu Office

Location: City. Dong Xoai, Binh Phuoc
Year of Commissioning: 2025
Status: Completed

Project Media Gallery

Installing smart LAN & WiFi system at Minh Thu Office

Site Logs & Engineering Solutions

Quy hoạch hạ tầng tủ Rack Server 42U, đi dây mạng Cat6A âm tường và hệ thống WiFi Mesh chịu tải 500 kết nối đồng thời.

Project Deployment Schedule

Week 1

Kick-off & Physical Survey

Delivery of camera units, LAN cabling media, ANPR systems, and GPS trackers to the site.

Week 2

Cable Tray & Path Execution

Technical crew routing cabling through protective insulated conduits for safety and aesthetics.

Week 3

Hardware Setup & Configuration

Mounting camera hardware, mapping local IP routes, configuring network routers, and systems integration.

Week 4

Acceptance Testing & Handover

Measuring throughput and data latency, handing over as-built cabling diagrams, and signing off reports.