Project Deployment Schedule

Week 1

Kick-off & Physical Survey

Delivery of camera units, LAN cabling media, ANPR systems, and GPS trackers to the site.

Week 2

Cable Tray & Path Execution

Technical crew routing cabling through protective insulated conduits for safety and aesthetics.

Week 3

Hardware Setup & Configuration

Mounting camera hardware, mapping local IP routes, configuring network routers, and systems integration.

Week 4

Acceptance Testing & Handover

Measuring throughput and data latency, handing over as-built cabling diagrams, and signing off reports.