Light electrical construction for Binh Duong Plastic Factory
Location: VSIP II Industrial Park, Ben Cat, Binh Duong
Year of Commissioning: 2026
Status: Completed
Project Media Gallery

Site Logs & Engineering Solutions
Thi công đồng bộ hệ thống cửa từ Access Control, âm thanh thông báo và kiểm soát chấm công vân tay cho 800 công nhân.
Project Deployment Schedule
Week 1
Kick-off & Physical Survey
Delivery of camera units, LAN cabling media, ANPR systems, and GPS trackers to the site.
Week 2
Cable Tray & Path Execution
Technical crew routing cabling through protective insulated conduits for safety and aesthetics.
Week 3
Hardware Setup & Configuration
Mounting camera hardware, mapping local IP routes, configuring network routers, and systems integration.
Week 4
Acceptance Testing & Handover
Measuring throughput and data latency, handing over as-built cabling diagrams, and signing off reports.